Wall-Plate Services & Implementation Project

CICS NetServices OpenSystems Security Telecom z/OS

Wall-Plate Services & Implementation Project

What is "Wall-Plate Service?"

Computing and Networking Services (CNS) is responsible for the design, installation, operation, and maintenance of the core network on the University of Florida campus. Core network services are funded centrally and provided to all campus units at no charge.

Core network services include:

Colleges, departments, and administrative units are responsible for providing local network connections within their buildings. As an alternative to "do-it-yourself," CNS began offering Network Services to the Wall-Plate for a monthly fee.

Standard Wall-Plate services include:

Wall-Plate Service Level Objectives [PDF]

What is the "Wall-Plate Project?"

Computing and Networking Services (CNS) now manages 40% of the local networks on the main campus (12,000 of 30,000 ports). On July 1, 2007 CNS will begin a 3-year project to upgrade the remaining 18,000 ports. This OIT sponsored, centrally funded, strategic technology initiative is known as the Wall-plate Project.

As announced last Fall, most academic and administrative units on the main campus are included in the Wall-Plate project. Externally funded auxiliary operations are not eligible. Housing, Shands, and the Health Sciences Center networks are self-supporting and not covered by the central funding.

The project will proceed building-by-building across campus. CNS will do the "quick and easy" projects first. Buildings with major wiring problems will be done last. To find out where your building(s) fit in the year-by-year schedule, please check the Implementation Schedule [PDF]. Units willing to provide additional funding to outsource the wiring upgrade can speed up their implementation.

Shortly before work in a building begins, all units that occupy the building will be asked to "opt-in" to the Wall-Plate Service, and select their desired service level.

Budget

The Wall-Plate project budget is $1,500,000 per year.

Equipment upgrades include the data networking devices that reside within a building, such as workgroup switches, wireless access points, and at least one Building-Point-of-Presence (BPOP).

Infrastructure upgrades include the telecom closets, the racks and patch panels in the closets, minor improvements to the wiring within a building, and additional fiber to the building as needed.

Support staff include 3 teams with 3-persons each, dedicated to working on the Wall-Plate project. 9 FTE in total.

The $1,500,000 per year provides a "steady-state" funding and staffing level. Enough to upgrade (replace) 6,000 ports per year. 30,000 ports total, over a 5-year lifecycle.

Implementation Schedule (by building)

Note that due to the nature of this work, roll-out is scheduled building-by-building, rather than by department or other organizational unit. You will need to look up the individual physical building(s) in which your unit is housed in order to determine when implementation will be available.

Complete Implementation Schedule (by Building) [PDF]

Building Schedule Update: 9/18/2009

Current Status

BuildingAnticipated Customer CommitmentPlanned Project CompletionActual Customer CommitmentActual Project CompletionImplementation Lead/Contact
Band BuildingNew Construction7/3/08NA7/25/08Mary Byrd
McCarty D10/8/0710/31/089/25/0711/30/08Mary Byrd
746 Particle Science11/2/0711/3/089/4/083/23/09Mary Byrd
Particle Science Annex11/2/0711/3/089/4/083/23/09Mary Byrd
Williamson / Kelvin11/30/077/17/0912/6/078/7/09Mary Byrd
SW Rec Center2/11/087/24/083/26/088/18/08Plant Rodgers
Florida Gym5/27/0810/16/088/12/0811/27/08Sheard Goodwin
Fisheries/ Aquatics6/1/089/26/086/1/089/26/08Plant Rodgers
Student Rec Center9/22/088/26/083/26/088/19/08Plant Rodgers
Carlton10/6/081/8/09NA11/21/08Sheard Goodwin
Dauer10/13/082/26/0910/31/083/3/09Sheard Goodwin
Microbiology10/20/082/12/096/30/0812/5/08Plant Rodgers
Academic Advising11/17/083/19/092/4/095/6/09Plant Rodgers
Physics12/10/0810/1/095/15/09 Sheard Goodwin
Stadium1/12/098/6/094/10/098/17/09Plant Rodgers
Norman1/14/096/12/091/14/096/30/09Plant Rodgers
Norman NE Suite Renovation1/14/09TBD1/14/09 Plant Rodgers
Norman G305,G513,HVAC Renovation1/14/096/30/091/14/099/11/09Plant Rodgers
Turlington10/30/092/5/09  Mary Byrd
Rolfs1/22/103/25/10  Mary Byrd
Tigert University RelationsNA8/6/094/10/095/22/09Plant Rodgers
Law AdvocacyNew Construction7/1/09NA Plant Rodgers
Law Layer 3 RetrofitPrior to WP Proj.6/7/09NA8/14/09Plant Rodgers
SW GarageNew Construction8/5/09NA Plant Rodgers
Hough HallNew Construction12/28/09NA Plant Rodgers
Entomology Nematology4/1/098/5/094/3/099/9/09Sheard Goodwin
Bartram / Carr4/15/0910/16/096/4/09 Sheard Goodwin
MAE #7195/4/0911/28/096/11/09 Plant Rodgers
Yon5/20/0910/23/096/1/09 Sheard Goodwin
New Engineering6/11/0911/14/096/26/09 Plant Rodgers
Black6/24/0911/30/097/16/09 Mary Byrd
Grinter7/30/099/20/09  Plant Rodgers
Walker10/2/0911/24/09  Sheard Goodwin
Fifield10/7/092/20/10  Sheard Goodwin
Fifield Compound10/7/092/20/10  Sheard Goodwin
PPD 700-709,270,809,827,54610/9/094/1/10  Sheard Goodwin
SSRB11/9/0912/29/09  Sheard Goodwin
McCarty A11/11/0912/31/09  Plant Rodgers
McCarty B11/11/0912/31/09  Plant Rodgers
BLDG 16211/11/0912/31/09  Plant Rodgers
BLDG 8711/11/0912/31/097/31/098/21/09Plant Rodgers
BLDG 81011/11/0912/31/09  Plant Rodgers
McCarty C12/14/092/14/10  Sheard Goodwin
Aquatic Food Production12/26/092/15/10  Mary Byrd
Reed Lab12/29/093/1/10  Mary Byrd
University Auditorium1/2/102/8/10  Mary Byrd
Benton1/13/102/18/10  Plant Rodgers
Peabody2/14/104/24/10  Mary Byrd
Food Science Human Nutrition3/6/105/25/10  Mary Byrd
Little3/13/105/25/10  Mary Byrd
Harn3/24/105/13/10  Plant Rodgers
Chemical Engineering4/17/106/8/10  Mary Byrd
Newell4/24/106/15/10  Mary Byrd
CSE5/3/1010/17/10  Sheard Goodwin
Chemistry Lab Building5/6/107/25/10  Sheard Goodwin
Larsen6/3/107/8/10  Sheard Goodwin
Leigh6/21/109/15/10  Mary Byrd
Chemistry Research7/10/109/15/10  Sheard Goodwin
Asian Arts CenterNew ConstructionTBDNA Mary Byrd
New InfirmaryNew ConstructionTBD  Sheard Goodwin
WeilTBDTBD  Plant Rodgers
PhelpsDeclined   Mary Byrd
Nuclear SciencesDeclined   Mary Byrd
MAE-B #720Declined   Plant Rodgers
MAE-A #725Declined   Plant Rodgers
MAEC LabDeclined   Sheard Goodwin

Announcements

Port Pricing

10/100 Megabits
The standard port connection speed is 10/100 Megabits -- provided at no charge.
10/100 Megabits + PoE (Power over Ethernet)
Power Over Ethernet switch upgrade -- provided at no charge. Note that a PoE port is required for VoIP service.
Gigabit Ethernet
Available for an extra 1-time, up-front charge of $600 per 24 ports. This represents the differential cost of installing a Gigabit switch as opposed to the standard 10/100 Megabit switch.
Gigabit Ethernet + PoE
Available for an extra 1-time, up-front charge of $1200 per 24 ports. This represents the differential cost of installing a Gigabit switch as opposed to the standard 10/100 Megabit switch.

Telephone Handset Pricing

Please refer to linked PDF

Frequently-Asked Questions

  • General Questions
  • Policy Questions
  • Schedule Issues
  • Building Issues
  • Data-Port Issues
  • VoIP Issues
  • For More Information

    If you have questions about Wall-Plate Services, or VoIP telephone services, please contact:

    John Madey
    jmadey@ufl.edu
    352.273-1113

    If you have questions about the Wall-Plate implementation project, please contact:

    Tim Fitzpatrick
    timf@ufl.edu
    352.392-2061

    Documentation

    DOCWEB: The CNS Documentation Library
    CNS Guidebook for New Users

    Overview of CNS
    Systems & Services


    Newsletters

    /Update: CNS Newsletter
    IT Connections; UF-OIT Newsletter

    Training